Location & field data
The block is spread over an
area of 500 sq. km located in the coaliferous
belt of the Eastern Raniganj Coalfields. The estimated
reserves are about 42 BCM.
Ownership
Essar has 100% ownership, with
Gardes Energy, US as the drilling technology partner.
Current status
- Work programme includes 120 LKM of 2D HRSS,
drilling of 12 core holes and 15 test wells
- Planning for first under-balanced horizontal
multi-lateral well is underway
Research & Development
Essar was the first Indian company
to recognise the potential of CBM in India in
the late 1980s and wanted to undertake CBM drilling.
Discussions were held with various CBM producers
in the USA and a study was closely monitored by
ARI. Three wells were drilled, hydro-fractured
and de-watered in Cambay Basin to successfully
test the lignito-bituminous coals. The economic
viability of the project has been established.
The efforts were supported by GIIC; the project
was sponsored by USAID under PACER.
|